Seaham Colliery boiler accident, 1901
A new Lancashire boiler slipped off its chocks while being set at Seaham Colliery on 18 March 1901, crushing a fitter and a driller to death.
| Date | 18 March 1901 |
|---|---|
| Mine | Seaham Colliery |
| Region | County Durham |
| Type | Machinery |
| Fatalities | 2 (Two killed: the fitter Mark Forster and the driller John William Milbourne Nixon.) |
| Context | During active mining |
Location
Plotted at Seaham Colliery. Recorded location. The large pin is the mine; the small round markers are the nearest mines on record. Click one for its page. View on full map
Cause
The chocks under a new Lancashire boiler gave way while it was being set.
What happened
On 18 March 1901 men at Londonderry Collieries' Seaham Colliery were setting a new Lancashire boiler. The chocks on which it rested gave way, and the boiler fell, catching and crushing two of them: the fitter Mark Forster, 24, and the driller John William Milbourne Nixon, 21. It was the fourth of four new boilers. It had been set, but one chock was found to be in the way of a flue still to be built. A hydraulic jack was put under the front end and the boiler raised about an inch, and four men went under it, two at each side, to move the chock. They had almost done it when the boiler lurched to one side and fell, killing one man on the spot and injuring the other so badly that he died within two hours.
Investigation & inquiry
The work was under the colliery's enginewright, who had 25 years' experience there and had erected or moved twelve boilers. He told the inquest the jack had stood on a level foundation, perfectly plumb, with a man left to watch it. The inspector, R. D. Bain, recorded it as No. 105 in his 1901 report (Cd 1062), page 45.
Recorded claims
Individual factual claims, each attached to the source(s) that support it below. Where sources disagree, both are kept.
- On 18 March 1901 the fitter Mark Forster, 24, and the driller John William Milbourne Nixon, 21, were crushed to death at Seaham Colliery when a new Lancashire boiler they were helping to set fell off its chocks. 1,2
- The chocks on which the boiler rested gave way, and the boiler caught and crushed the two men as it fell. 1,2
- The colliery belonged to Londonderry Collieries Ltd. 2
- The boiler had been raised about an inch on a hydraulic jack so that four men could move a chock from under it when it lurched and fell. 3
- One man was killed on the spot and the other died within two hours. 3
- The work was supervised by the colliery enginewright, who said the jack was level, plumb and watched. 3
Related terminology
Mining terms this disaster is structurally linked to, with the nature of the relationship.
- Colliery (contextual relationship)
Named 3 times in this record, first in the summary: “…Lancashire boiler slipped off its chocks while being set at Seaham Colliery on 18 March 1901, crushing a fitter and a driller to death.” - Lancashire Boiler (contextual relationship)
Named 3 times in this record, first in the summary: “A new Lancashire boiler slipped off its chocks while being set at Seaham Colliery on 18…” - Level (contextual relationship)
Named in this record’s investigation: “…or moved twelve boilers. He told the inquest the jack had stood on a level foundation, perfectly plumb, with a man left to watch it. The…”
Sources
- (primary) Durham Mining Museum: Seaham Colliery — Durham Mining Museum
- (secondary) 1900s F2: Ian Winstanley's alphabetical list of mining victims — Healey Hero
- (primary) Mark Forster, Seaham, 18 March 1901: the inspector's account — Durham Mining Museum
Record created: 8 October 2026 · Last researched: 31 October 2026